How Much Contingency Should You Allow for a Property Refurbishment?

A refurbishment budget tells you what you expect the works to cost. A contingency prepares you for what you didn't expect. The right allowance depends on the property, the project and how much uncertainty you're taking on.

PROPERTY THESIS · INVESTOR LIBRARY

8 MIN READ

Brick renovation property exterior

What is a refurbishment contingency?

A refurbishment contingency is money set aside within the project budget to cover costs that weren’t fully anticipated when the original estimate was prepared.

Imagine you’ve budgeted:

Refurbishment works: £40,000

You could proceed on the assumption that the final bill will be exactly £40,000.

Or you could recognise that renovation involves uncertainty and allocate additional capital for unexpected costs.

That’s your contingency.

Importantly, contingency shouldn’t be treated as money you’re planning to spend.

It’s protection against the project costing more than expected.

Is 10% contingency enough?

You’ll often hear investors use 10% as a rule of thumb.

It can be a useful starting point.

But there isn’t one contingency percentage that’s appropriate for every refurbishment.

Consider two projects.

PROJECT A

A relatively modern property requiring:

  • decoration

  • flooring

  • a new kitchen

  • a new bathroom

  • minor external works

PROJECT B

A much older property requiring:

  • structural alterations

  • complete electrical works

  • new plumbing and heating

  • roofing work

  • damp investigation

  • new windows

  • major internal reconfiguration

Applying exactly the same contingency approach to both projects ignores the enormous difference in uncertainty.

The more you don’t know about the property, the more important contingency becomes.

Start with the quality of your original budget

A percentage contingency doesn’t rescue a poor refurbishment estimate.

If the project is likely to cost £60,000 but you’ve entered £40,000 into the spreadsheet, adding a 10% contingency gives you £44,000.

You don’t have a contingency problem.

You have a budgeting problem.

Before deciding how much contingency to hold, make the base refurbishment budget as realistic as possible.

Break the project into individual workstreams.

For example:

  • demolition and clearance

  • structural works

  • roofing

  • windows and doors

  • electrical

  • plumbing and heating

  • kitchen

  • bathrooms

  • plastering

  • carpentry

  • decoration

  • flooring

  • external works

  • professional fees

  • waste removal

  • scaffolding

Then add contingency to a budget you actually believe.

Why refurbishment costs increase

Projects exceed budget for several different reasons.

HIDDEN DEFECTS

Some problems only become visible once work begins.

Floorboards come up.

Walls are opened.

Old fittings are removed.

Suddenly the building tells you considerably more about itself than it did during the viewing.

SCOPE CHANGES

You decide to improve the specification or undertake additional work during the project.

That’s not necessarily an unexpected cost.

It’s a change to the project.

ESTIMATING ERRORS

The original budget simply underestimated the amount of labour or materials required.

PRICE CHANGES

Material, labour or subcontractor costs can change between estimating the project and completing the work.

DELAYS

A longer project can increase finance, insurance, utilities and other holding costs even if the building work itself remains close to budget.

These risks should be considered separately rather than hiding everything inside one contingency figure.

A simple percentage approach

For early-stage investment analysis, applying a percentage to the refurbishment budget can be useful.

For example:

Base refurbishment budget: £50,000

At a hypothetical 10% contingency:

£50,000 × 10% = £5,000

Total works allowance:

£55,000

If you wanted to test a more conservative scenario at 20%:

£50,000 × 20% = £10,000

Total works allowance:

£60,000

The purpose isn’t to decide that either percentage is universally correct.

It’s to understand what a cost overrun does to the investment.

Contingency should reflect uncertainty

Rather than choosing a percentage automatically, think about the project’s unknowns.

Ask:

  • How old is the property?

  • How much can actually be inspected?

  • Are structural alterations planned?

  • Is there evidence of damp or movement?

  • What condition are the roof and drainage in?

  • How old are the electrics?

  • How old is the heating system?

  • Are there previous alterations?

  • Is planning or building control involved?

  • How detailed are the contractor quotations?

  • Has an appropriate survey been carried out?

  • How experienced is the project team?

As uncertainty reduces, your understanding of the likely costs should improve.

Separate building contingency from holding-cost contingency

This is an important distinction.

Imagine a refurbishment is expected to take four months.

Your building works might stay within budget.

But if the project takes six months instead, you may incur another two months of:

  • mortgage or bridging interest

  • council tax where applicable

  • utilities

  • insurance

  • security

  • storage

  • other project costs

A building contingency doesn’t necessarily account for a time overrun.

For a financed refurbishment, both cost risk and time risk should be modelled.

Don’t forget professional and statutory costs

The contractor’s quote isn’t necessarily the complete refurbishment budget.

Depending on the project, you may also need to consider costs associated with:

  • architects

  • structural engineers

  • surveyors

  • planning

  • building control

  • party wall matters

  • specialist reports

  • warranties or certification

Not every project requires all of these.

But excluding relevant professional costs can make a project appear cheaper than it really is.

Contingency affects your return

Imagine:

Purchase price: £250,000

Acquisition and finance costs: £20,000

Refurbishment: £50,000

Expected total project cost:

£320,000

Expected finished value:

£375,000

On the initial numbers, there appears to be:

£55,000

between project cost and finished value.

Now suppose refurbishment costs increase by 20%.

Works become:

£60,000

Total project cost becomes:

£330,000

The gap has reduced to:

£45,000

And that’s before considering tax, selling costs, refinance costs or any other amounts relevant to the strategy.

The end value hasn’t changed.

The property hasn’t changed.

But your economics have.

What if costs rise and the end value falls?

This is where stress testing becomes particularly powerful.

Investors often analyse risks individually.

But problems don’t always arrive individually.

Consider:

BASE CASE

Refurbishment: £50,000

End value: £375,000

DOWNSIDE CASE

Refurbishment: £60,000

End value: £350,000

Your costs have increased by £10,000 at exactly the same time as your expected value has fallen by £25,000.

The investment case has moved by £35,000.

That’s far more revealing than simply adding 10% contingency to the works.

Contingency is also a capital question

It’s possible to have a profitable project on paper and still run into difficulty because you don’t have enough cash to finish it.

Suppose the project requires £50,000 of refurbishment.

You have exactly £50,000 available.

If an unexpected £7,000 problem emerges, where does that money come from?

Additional borrowing may not be available.

Selling halfway through a refurbishment may be unattractive.

Delaying works can create further holding costs.

Contingency therefore isn’t only about protecting your projected return.

It’s about making sure you have enough capital to complete the strategy.

Don’t spend the contingency before you need it

There’s another trap.

A project is progressing well and the contingency hasn’t been used.

So the specification starts improving.

More expensive flooring.

A better kitchen.

Additional landscaping.

Suddenly the contingency has become an upgrade budget.

Then a genuine unexpected problem appears.

The money has already gone.

Keep contingency separate from planned improvements.

If it’s still unused when the project finishes, that’s a good result.

The Property Thesis approach

We wouldn’t look at a refurbishment contingency in isolation.

We’d test the complete project.

BASE WORKS

What should the planned refurbishment realistically cost?

CONTINGENCY

What additional capital is available for unexpected building costs?

TIMESCALE

What happens if the project takes longer?

CAPITAL

Is sufficient cash available to complete the project if costs increase?

END VALUE

What happens if the finished property is worth less than expected?

FINANCE

How do additional costs or delays affect borrowing and interest?

EXIT

Does the sale or refinance still work under a downside scenario?

The objective isn’t to predict every problem that might occur.

That’s impossible.

The objective is to build an investment case that doesn’t require everything to go perfectly.

Related resources

The objective is to build an investment case that doesn't require everything to go perfectly.

Frequently asked questions

What is a refurbishment contingency?

A refurbishment contingency is additional money set aside to cover costs that weren't fully anticipated within the original renovation budget.

Is 10% enough contingency for a property renovation?

There is no single percentage appropriate for every project. A percentage such as 10% can be useful for scenario planning, but the appropriate allowance depends on the property's condition, project complexity and level of uncertainty.

Should contingency be included in my total project cost?

Yes. If the capital may be required to complete the project, it should form part of your assessment of the project's potential cash requirement rather than being ignored because you hope not to spend it.

Should I allow for renovation delays as well as cost overruns?

Yes. A project taking longer than expected can increase finance, utilities, insurance and other holding costs even when the building works remain close to budget.

What happens to my contingency if I don't use it?

If the project is completed without using the contingency, the unused capital hasn't become a project cost. That can improve the eventual return compared with the downside scenario you allowed for.

ANALYSING A REFURBISHMENT?

See what happens when the budget moves.

Property Thesis Analyse is designed to stress test refurbishment costs, end value, finance and exit assumptions so you can understand whether the investment still works when the project doesn't go exactly to plan.

Build Your First Property Thesis — Free

Property Thesis provides research and analysis tools for informational purposes. Content does not constitute mortgage, investment, tax, legal, valuation, surveying, planning or building advice. Property values, refurbishment costs, rental income and finance availability are assumptions that require appropriate due diligence and professional advice where relevant.

PROPERTY THESIS — INVESTOR BRIEFING

Property analysis worth opening.

Get new property analysis, investment insights, practical tools and market observations delivered to your inbox.

No noise. Unsubscribe anytime.

PROPERTY THESIS — INVESTOR BRIEFING

Property analysis worth opening.

Get new property analysis, investment insights, practical tools and market observations delivered to your inbox.

No noise. Unsubscribe anytime.